Lancaster General Hospital Parking Garage & Front Entrance
The Parking Garage and Entrance Lobby is a 155,000 square foot addition for Lancaster General Hospital. This project consisted of a new public and employee parking garage as well as a new front entrance lobby to the Hospital.
One of many challenges on the project was the removal of our 1,200 cubic yards of rock right next to a working hospital. Another challenge was the logistics of delivering and erecting foot long concrete deck pieces to a downtown location. Both tasks required constant communications between LGH staff and Benchmark in order to facilitate the daily schedule of the Hospital.
Construction was completed in just nine months and the new two-story atrium lobby now greets patients and visitors. The five-level garage provides a total of 338 parking spaces, which is accessible directly to the ground, first and second floor of the Hospital.
|
 |
Location: Lancaster, PA
Design Professionals: Ewing Cole Cherry Brott
Total SF: 155,000 SF
Value: $ 6.3 Million
Awards:
2001 ABC - Keystone Chapter AWARD OF EXCELLENCE
Services Provided: Construction Management and General Construction Services
| “Benchmark is consistent in meeting aggressive schedules with complex phasing. Benchmark sees to it that they have the best staff and subcontractors for the project and don’t hesitate to make adjustments appropriate for maintaining the schedule or taking on
challenges which require special project expertise. Based on these experiences, as well as positive feedback we have gotten from our clients, we will recommend Benchmark with high commendations to anyone who may consider them for a construction project.